" Officer grants a further period of time before the date of final payment under the contract), notifies the Contracting Officer in . writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend... "
The Code of Federal Regulations of the United States of America - Página 213
1982
Vista completa - Acerca de este libro

Cases Decided in the Court of Claims of the United States, Volumen111

United States. Court of Claims - 1948 - 886 páginas
...beginning of any such delay, or such longer period as may be allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes of...judgment the findings of fact justify such an extension. The decision of the Contracting Officer thereon shall be final, subject only to appeal under Article...
Vista completa - Acerca de este libro

Cases Decided in the United States Court of Claims ... with ..., Volumen115

United States. Court of Claims, Audrey Bernhardt - 1950 - 940 páginas
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...
Vista completa - Acerca de este libro

Cases Decided in the Court of Claims of the United States, Volumen94

United States. Court of Claims - 1942 - 818 páginas
...the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...fact justify such an extension, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Vista completa - Acerca de este libro

Cases Decided in the Court of Claims of the United States, Volumen107

United States. Court of Claims - 1947 - 806 páginas
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...of fact justify such an extension, and his findings pi fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within...
Vista completa - Acerca de este libro

Cases Decided in the Court of Claims of the United States, Volumen105

United States. Court of Claims - 1946 - 920 páginas
...liquidated damages because of unforeseeable causes of delay, including strikes, and it provides that the contracting officer "shall ascertain the facts...judgment the findings of fact justify such an extension." This, of course, makes it mandatory upon the contracting officer to make findings of fact upon an application...
Vista completa - Acerca de este libro

Cases Decided in the United States Court of Claims ... with ..., Volumen152

United States. Court of Claims, Audrey Bernhardt - 1963 - 938 páginas
...beginning of any such delay, or such longer period as may be allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes of...delay and extend the time for completing the work or any part thereof when in his judgment the findings of fact justify such an extension. The decision...
Vista completa - Acerca de este libro

Cases Decided in the Court of Claims of the United States, Volumen104

United States. Court of Claims - 1946 - 936 páginas
...contract) notify the contracting officer in writing of the causes 01 delay, who shall ascertain the fact and the extent of the delay and extend the time for...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...
Vista completa - Acerca de este libro

Cases Decided in the United States Court of Claims ... with ..., Volumen123

United States. Court of Claims, Audrey Bernhardt - 1958 - 1044 páginas
...notify the contracting officer in writing of the causes of the delay, who shall ascertain the facts and extent of the delay and extend the time for completing...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...
Vista completa - Acerca de este libro

Cases Decided in the United States Court of Claims ... with ..., Volumen114

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 páginas
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...his judgment the findings of fact justify such an extensionj and his findings of fact thereon shall be final and conclusive on the parties hereto, subject...
Vista completa - Acerca de este libro

Cases Decided in the Court of Claims of the United States, Volumen109

United States. Court of Claims - 1948 - 974 páginas
...delay, who shall ascertain the facts and the extent of the 109 C. Clg. Reporter's Statement of the Case delay and extend the time for completing the work...justify such an extension and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...